EMISSION CONTROL & ACOUSTICS
SCR, Exhaust Purification and Engine Room Noise Treatment
Emissions Are Specified, Not Assumed
Emission and noise limits are set by the site's permit, not by the equipment catalogue. The same generator set may be acceptable at one location and refused a permit a few kilometres away, because the limit that applies is written into the local air quality or environmental noise regulation and is enforced at the boundary, not at the exhaust pipe.
Three things get regulated, and they are solved by three different systems. Nitrogen oxides are dealt with by selective catalytic reduction on the exhaust. Smoke and particulate matter are dealt with by combustion quality and exhaust purification. Noise is dealt with by the enclosure, the room and the exhaust silencer together. Treating them as one "environmental package" is how plants end up compliant on one parameter and non-compliant on another.
| Parameter | Measured at | Controlled by |
|---|---|---|
| NOx | Exhaust stack, corrected to 5% O&sub2; | SCR with urea reagent, or lean-burn combustion where the limit allows |
| Smoke opacity | Stack outlet, Ringelmann chart | Injection timing, load acceptance rate, exhaust purification |
| Particulates | Stack, gravimetric sampling | Combustion quality, filter or trap where fitted |
| Noise | Site boundary, or 1 m / 7 m from the enclosure | Enclosure, room absorption, silencer, vibration isolation |
Before anything is specified, we ask for the actual limit text from the permit, including the oxygen correction basis and the reference distance. A limit quoted without those two details cannot be designed against, and a system designed to the wrong basis will pass on paper and fail at the stack.
SCR Denitrification — NOx Down to 30 mg/Nm³
Selective catalytic reduction injects a reducing agent into the exhaust upstream of a catalyst, where it reacts preferentially with nitrogen oxides and turns them into nitrogen and water. The reagent is ammonia, carried as urea solution because urea is far safer to store and handle on an industrial site than anhydrous ammonia.
Two stages happen before the catalyst does any work. Urea thermally decomposes to ammonia and isocyanic acid, and the isocyanic acid hydrolyses to ammonia and carbon dioxide. Only then is ammonia available to react with NO and NO₂ over the catalyst. If the injection point is too cold or the mixing is poor, the reagent never becomes ammonia where it needs to be, and the result is ammonia slip rather than NOx reduction.
| Stage | Reaction | Where it happens |
|---|---|---|
| Urea thermolysis | CO(NH₂)₂ → NH₃ + HNCO | In the hot exhaust, immediately after injection |
| Urea hydrolysis | HNCO + 2H₂O → NH₃ + CO₂ | Same zone, before the catalyst face |
| Standard SCR | 4NH₃ + 4NO + O₂ → 4N₂ + 6H₂O | On the catalyst surface |
| Fast SCR | 4NH₃ + 2NO₂ + 2NO → 4N₂ + 6H₂O | On the catalyst surface, where NO₂ is present |
| Duty | NOx at 5% O&sub2; | Ammonia slip |
|---|---|---|
| Standard | ≤ 75 mg/Nm³ | ≤ 2.5 mg/Nm³ |
| Enhanced | ≤ 30 mg/Nm³ | ≤ 2.5 mg/Nm³ |
The system is supplied as skid-mounted modules, each with its own dosing, control and instrumentation, so a plant can run several modules in parallel and keep a high overall availability if one goes down for catalyst replacement. Catalyst life depends on fuel sulphur and oil consumption: an engine burning high-sulphur fuel will poison its catalyst long before its mechanical overhaul, and that cost belongs in the operating budget, not the capital budget.
Exhaust Gas Purification — Smoke and Particulates
Smoke is the visible symptom of incomplete combustion, and it is regulated both as opacity and, on some permits, as a particulate mass limit. The first line of defence is the engine itself: injection timing, fuel quality, and how fast load is applied. A set that accepts a full load step in two seconds will smoke; the same set ramped over fifteen seconds will not.
Beyond combustion control, exhaust purification deals with what is left. The target most permits work to is a Ringelmann smoke number below 1, which is effectively invisible against a light background. Achieving it consistently means the purification stage has to be matched to the engine's actual soot output at the loads the plant really runs, not at the load printed on the datasheet.
| Measure | Target | Method |
|---|---|---|
| Smoke opacity | Ringelmann < 1 | Combustion tuning plus exhaust purification, verified at load steps |
| Particulate mass | Per permit, gravimetric | Filtration or trapping where the mass limit cannot be met by combustion alone |
| Load acceptance rate | Ramp set to the smoke limit, not the fastest possible | Controller ramp configuration, verified during commissioning |
Where a plant is required to meet a limit that combustion tuning alone cannot reach, the purification stage is designed with the engine rather than bolted on afterwards, because back pressure, temperature and regeneration all interact with the engine's own operating envelope.
Engine Room Acoustics — Six Elements of a Quiet Plant
Noise from a generator plant leaves through more paths than the exhaust. Structure-borne vibration travels through the foundation into the building fabric; airborne noise escapes through walls, ceiling, doors and cable penetrations; and the exhaust carries both the firing frequency and the broadband hiss of the turbo. Treating one path and leaving the others is why plants measure worse than the sum of their parts suggests.
We work the acoustic design as six linked elements. Each one has a measurable target, and each one is worthless if the others are left open.
| # | Element | What it controls |
|---|---|---|
| 1 | Exhaust gas purification | Smoke and particulates at the stack |
| 2 | Exhaust silencer | Firing frequency and exhaust broadband noise |
| 3 | Wall and ceiling absorption | Reverberant build-up inside the room, which otherwise leaks out through every opening |
| 4 | Vibration and damping | Structure-borne transmission into the building and the ground |
| 5 | Oil supply, return and tank | Noise and smell from the fuel system, and the fire risk that comes with it |
| 6 | Integrated acoustic design | Doors, penetrations, ventilation paths and the sequence of the other five |
Two construction details matter more than they look. The ceiling grid should be walkable and rated above 150 kg per point, because acoustic panels get serviced and a non-walkable ceiling turns a minor maintenance job into a scaffold. And the materials should be colour-matched so that repairs do not leave a visible patch — acoustic treatment that looks like a repair tends to get removed by the next contractor who needs access.
Sound Pressure Targets by Distance
Noise is specified as sound pressure at a stated distance, and the distance changes the number by more than most people expect. A set measuring 85 dB(A) at 1 m will measure roughly 72 dB(A) at 7 m, because sound pressure falls about 6 dB per doubling of distance in free field. Quoting a figure without the distance is meaningless.
The table below gives the enclosure classes we build to, with the acoustic performance and the envelope that goes with it. Larger sets need more absorption material and more enclosure volume for the same attenuation, which is why the physical size climbs faster than the power rating.
| Enclosure class | @ 1 m dB(A) | @ 7 m dB(A) | L × W × H (mm) | Weight (kg) |
|---|---|---|---|---|
| S20–S70 | 78 | 72 | 2370 × 1100 × 1650 | 680 |
| S80–S100 | 78 | 72 | 2900 × 1100 × 1650 | 870 |
| S120–S132 | 78 | 72 | 3200 × 1200 × 1750 | 950 |
| S160–S180 | 80 | 75 | 3500 × 1300 × 1900 | 1040 |
| S200 | 80 | 75 | 3600 × 1350 × 2100 | 1260 |
| S220–S360 | 80 | 75 | 4200 × 1400 × 2150 | 1680 |
| S400–S520 | 90 | 85 | 4500 × 1600 × 2500 | 1800 |
| S550 | 90 | 85 | 5000 × 1800 × 2450 | 2000 |
| S640–S800 | 90 | 85 | 5800 × 2200 × 2600 | 2800 |
Note the step at S400: the class goes from 80 to 90 dB(A) at 1 m. That is not a decline in build quality, it is physics — above roughly 400 kW the enclosure cannot absorb enough of the engine's output without becoming impractically large. If a permit requires 80 dB(A) at 1 m on a 500 kW set, the answer is a room with acoustic treatment rather than an enclosure, and the design changes accordingly.
Vibration Isolation and Foundation
Vibration is the noise path that most often gets left untreated, because it is invisible until someone stands in an office two floors away and hears a low-frequency hum that no amount of wall absorption will remove. Structure-borne noise has to be stopped at the source.
Isolation is a matter of matching the isolator's natural frequency to the disturbing frequency, with enough static deflection that the isolator is actually doing work rather than sitting solid. Undersized isolators transmit almost as much as no isolators at all, and they are worse than none because they give a false sense that the problem has been dealt with.
| Element | Requirement | Why |
|---|---|---|
| Foundation mass | Typically 1.5–2× the set mass, on a separate block where structure-borne limits are tight | Mass lowers the system's natural frequency away from the firing frequency |
| Isolator deflection | Static deflection sized to the set's mass distribution, not averaged | A set with an uneven mass distribution needs different isolators at different points |
| Flexible connections | Flexible exhaust bellows, flexible fuel and coolant lines, flexible cable entry | A rigid pipe bridging the isolator bypasses it completely |
| Inertia base | Where the building structure cannot take the mass of a separate block | Distributes load and lowers the centre of gravity of the isolated system |
Oil Supply, Return and Tank Engineering
The fuel system is part of the environmental scope, not just the mechanical scope. A day tank that vents into a room shared with acoustic panels is a smell problem and a fire problem at the same time, and both are avoidable at the design stage.
The arrangement we specify separates the storage tank from the engine room, feeds a day tank by an automatic transfer pump with high and low level alarms, and returns surplus fuel to the day tank rather than to the main storage. Return to the main tank is what aerates the fuel and what makes a small leak in the return line go unnoticed.
| Component | Function | Detail that matters |
|---|---|---|
| Main storage tank | Bulk storage, sized to the refuelling interval the site can live with | Bunded to 110% of capacity, vented outside, with level indication |
| Day tank | Short-run supply close to the engine, typically 4–8 hours of running | High/low level alarms and automatic transfer pump control |
| Supply and return lines | Deliver fuel at the engine's required pressure and temperature | Return to the day tank, not the main tank; leak detection on the run |
| Oil-water separation | Handles condensate and any water drawn from the tank | Drain points at the low points, not at the tank only |
| Fire protection | Isolation valves operable from outside the room | Remote emergency stop and fuel shutoff, clearly marked |
What We Need to Specify Your System
Environmental scope is quoted from the permit and the site, not from the set alone. The list below is what turns a budget number into a design.
| Input | Why it changes the design |
|---|---|
| Permit limits, with oxygen correction and reference distance | A limit without a basis cannot be designed against |
| Set model, rating and fuel | Exhaust flow, temperature and soot output all follow from this |
| Annual running hours and load profile | Reagent consumption, catalyst life and silencer duty all scale with hours |
| Distance to the nearest sensitive receptor | Decides whether enclosure alone is enough or room treatment is required |
| Building construction and shared structure | Structure-borne path and the need for a separate foundation block |
| Fuel storage arrangement and available footprint | Tank size, bunding and the route of supply and return lines |
Frequently Asked Questions
Do I need SCR for a diesel generator?
Only where the permit requires it. Many jurisdictions regulate stationary engines above a certain size, and the limit often cannot be met by combustion tuning alone. If the site is in a designated air quality zone or near a sensitive receptor, assume SCR is on the table and price it before choosing the set.
How often does SCR catalyst need replacing?
It depends on fuel sulphur and oil consumption more than on running hours. A set on low-sulphur fuel with good oil control can go several years between catalyst replacements; a set burning high-sulphur fuel will poison the catalyst much sooner. Sulphur in the fuel is the single biggest factor in catalyst life.
Can I meet a noise limit with an enclosure alone?
Up to roughly 400 kW at 80 dB(A) at 1 m, usually yes. Above that, or below that noise figure, the enclosure becomes impractically large and a treated room is the better answer. The decision point is the S400 class in the table above.
Why is 7 m the reference distance and not 1 m?
1 m is a standardised measurement point close to the source, useful for comparing enclosures. 7 m is closer to where people actually stand, and many site permits are written at that distance. We quote both so the number can be checked against whichever basis the permit uses.
Is vibration isolation really necessary on a small set?
On a ground-floor plant room with a slab on grade, often not. On an upper floor, next to an office, or above a basement, yes — and retrofitting it means lifting the set. It is much cheaper to decide at the design stage than to fix after the building is occupied.
Can emission and noise scope be added to an existing installation?
Usually yes, with two caveats. Retrofitted SCR needs space in the exhaust run and a reagent storage area, which existing plant rooms often do not have. Retrofitted acoustic treatment on a room is straightforward; retrofitted vibration isolation is not, because it requires lifting the set.