SAME DAY SHIPPING ON ALL STOCKED PRODUCTS
86-0769-89610677 / 86-13553838770 | info@jinjiadongli.com
500 kVA diesel generator set

500 kVA GENERATOR

JJP-M400GF — 500 kVA / 400 kW prime, 550 kVA / 440 kW standby. 722 A per phase at 400 V, 3500 × 1500 × 2000 mm, 2300 kg, 88.6 L/h at full load.

See the Full Specification
Other ratings in this range 100 kVA200 kVA250 kVA375 kVA500 kVAAll 50–625 kVA

500 kVA Generator — JJP-M400GF

Prime (PRP)
500 kVA
400 kW at 0.8 PF
Unlimited hours, 10% overload for 1 h in 12
Standby (ESP)
550 kVA
440 kW at 0.8 PF
Loss of mains only, 200 h/yr

500 kVA is the one round number in this range that maps exactly onto a standard frame. No oversizing, no compromise — the 500 kVA figure on the brief is the prime rating on the nameplate. 1500 rpm at 50 Hz, 1800 rpm at 60 Hz, three-phase four-wire, 0.8 power factor.

500 kVA Generator Dimensions and Weight

ConfigurationDimensions L × W × HWeight
Open skid3500 × 1500 × 2000 mm2300 kg
Silent canopy+300 mm per dimension → 4100 × 2100 × 2600 mm2480–2550 kg
With fuel (400 L tank)—+340 kg approx.

At 2.3–2.55 t this is a crane or heavy-forklift lift, not a pallet truck job. For a canopied set allow a 4.1 m × 2.1 m footprint plus 1 m clearance on the alternator end for cooling air, and cast a level concrete plinth rated for 1.5× the wet weight. Confirm door swing before siting — the lockable access panels open on both long sides.

How Many Amps Is a 500 kVA Generator?

VoltagePhaseCurrent at 500 kVASuggested breaker frame
380 V3-phase760 A1000 A
400 V3-phase722 A1000 A
415 V3-phase696 A800 A
440 V3-phase656 A800 A
480 V3-phase601 A800 A
220 V1-phase2273 Aspecial winding
240 V1-phase2083 Aspecial winding

I = kVA × 1000 ÷ (√3 × V). Breaker sizing at 125% of the 400 V figure gives 903 A, so a 1000 A frame is the usual choice. Cable at 722 A needs roughly 2 × 185 mm² copper per phase for a run under 50 m, or a busbar trunking system above that. Single-phase 500 kVA sets are not practical — balance across three phases instead.

Fuel Consumption per Hour

LoadOutputDiesel L/hUS gal/hPer kVA per hour
100% (prime)500 kVA / 400 kW88.6 L/h23.40.177 L
80%400 kVA / 320 kW70.9 L/h18.70.177 L
60%300 kVA / 240 kW53.2 L/h14.00.177 L
40%200 kVA / 160 kW35.4 L/h9.40.177 L
20%100 kVA / 80 kW17.7 L/h4.70.177 L

Based on ≤185 g/kWh at 835 g/L diesel density. Consumption is close to linear with load in this class, which makes the daily fuel bill easy to budget: hours × load fraction × 88.6 L. A set held at 40% load for 12 hours a day burns about 425 L — plan tank capacity and refuelling access around that number, not around full load.

Engine Options on the 500 kVA Frame

BrandEngine modelStandby outputCylindersDisplacement
CumminsQSK19-G13451 kW6-cyl19 L
WeichaiWP13D448E200448 kW6-cyl12.5 L
SDECG-series440 kW6-cyl16 L
Perkins2506A-E15TAG2440 kW6-cyl15 L
VolvoTAD1231GE425 kW6-cyl12.1 L

Coupled to a Leroy Somer LSA46.3S5 or Stamford HCI544 alternator. Deep Sea DSE7320 MKII controller as standard, DSE8610 for parallel operation. At this rating the engine choice drives both price and serviceability — Cummins QSK19 has the widest parts network in Africa and the Middle East; Weichai and SDEC are the cost-competitive options with strong regional support; Perkins and Volvo suit projects with emission or brand requirements.

What Can a 500 kVA Generator Power?

Factory or production line
300–340 kW of connected load. At this size the constraint is motor starting — check the largest DOL motor against the 10% overload window before confirming.
Hotel or shopping centre
250–350 rooms, or 8,000–10,000 m² of retail. Runs the whole building including HVAC and lifts without load shedding.
Hospital campus
200–300 beds with theatres, imaging and cold chain. Normally specified as 2 × 500 kVA in parallel for N+1.
Data centre or colocation
30–40 racks at 8–10 kW each, with UPS and cooling on the generator bus. Parallel configuration is standard here.
Water treatment or pumping
Large pump sets starting in sequence. Sequence the starts — two 200 kW pumps starting together will trip a 500 kVA set.
Construction or mining camp
Crushers, conveyors, camp accommodation and workshops. Specify the heavy-duty air filtration and a fuel polishing setup for dust.

Single Set or Two in Parallel?

At 500 kVA the redundancy question usually decides the project more than the price does. A single JJP-M400GF is the cheapest way to cover the load, but a single set is also a single point of failure. Two 250 kVA sets in parallel cost 15–25% more and give N+1: one set carries the essential load while the other is serviced, and both share load at peak.

ConfigurationCoverageRedundancyWhen it is right
1 × JJP-M400GF500 kVANoneFactory, hotel or site where a planned outage is acceptable
2 × 250 kVA parallel500 kVA sharedN+1Hospital, data centre, telecom — load must not drop
2 × JJP-M400GF parallel1000 kVAN+1 at 500 kVALoad above 500 kVA, or growth planned within 3 years

Parallel operation requires the DSE8610 controller, matching alternator pitch, a shared load bus and a synchronising panel. Retro-fitting parallel capability after delivery is expensive — decide it at the quote stage.

What Does a 500 kVA Generator Cost?

Open-skid JJP-M400GF sets run US$28,000–38,000 FOB China. Engine brand moves that band more than anything else — Cummins QSK19 and Perkins 2506A sit at the top, Weichai and SDEC at the bottom. A sound-attenuated canopy adds 8–12% and about 200 kg. Budget separately for a 1000 A breaker, an ATS if the site needs automatic transfer, a synchronising panel if two sets run in parallel, and freight — a 2.5 t canopied unit is a 40 ft container shipment with the fuel tank drained.

500 kVA Generator Questions

How many amps does a 500 kVA generator deliver?

722 A per phase at 400 V three-phase, 760 A at 380 V, 696 A at 415 V, 601 A at 480 V. Size the breaker at 125% of the 400 V figure — 903 A, so a 1000 A frame.

What does a 500 kVA generator weigh?

2300 kg on an open skid, 3500 × 1500 × 2000 mm. The silent canopy adds 180–250 kg and 300 mm per dimension, giving about 2.5 t before fuel. Add roughly 340 kg for a full 400 L tank.

How much fuel does a 500 kVA generator use per hour?

88.6 L/h at full 500 kVA load, 70.9 L/h at 400 kVA, 53.2 L/h at 300 kVA. That is 0.177 L per kVA per hour — consumption is close to linear with load in this class.

Is 500 kVA the same as 400 kW?

At 0.8 power factor, yes — 500 × 0.8 = 400 kW. If the load has a lower power factor, the usable kW drops further. Motors and transformers pull the PF down; check the site PF before confirming the rating.

Can two 500 kVA generators run in parallel?

Yes, with the DSE8610 controller, matching alternator pitch and a synchronising panel. Two sets give 1000 kVA total, or N+1 redundancy at 500 kVA. Decide this at the quote stage — retro-fitting is expensive.

Which engine is best at 500 kVA?

Cummins QSK19 for parts availability across Africa and the Middle East; Weichai WP13D or SDEC G-series for cost with strong regional support; Perkins 2506A and Volvo TAD1231 where emission compliance or brand specification matters.

What noise level does a 500 kVA set run at?

65–75 dB(A) at 7 m for the canopied set, depending on acoustic grade. Above 500 kVA, site noise limits usually call for a residential-grade canopy or an acoustic enclosure with a remote radiator.

Single phase or three phase?

Three-phase, always, at this rating. A single-phase 500 kVA winding would be a bespoke alternator pulling 2273 A at 220 V — impractical. If the site is single-phase, split the load across three phases.

What foundation does it need?

A level concrete plinth rated for 1.5× the wet weight, with anti-vibration mounts under the baseframe. Allow 1 m clearance at the alternator end for cooling air, and confirm canopy door swing on both long sides before siting.

Send the load schedule, get both configurations priced

Running kW, largest motor, and whether redundancy matters — we will quote the single 500 kVA set against the parallel option so the trade-off is visible.

Request a Quote